No.
|
Project Name
|
Start
|
Finish
|
Consultant/Architect
|
|
16
|
Power Plant Project Punjab
|
July-06
|
Mar-08
|
M/s. NESPAK
|
|
17
|
Power Plant Workshops, Cooling Tower Units
|
July-09
|
Dec-10
|
M/s. Pakistan Atomic Energy Commission
|
|
18
|
Lucky Cement Plant. 8400 TPD, Nooriabad
|
Sep-04
|
Jul-06
|
M/s. Loya Associates
|
|
19
|
Bosicor Oil Pakistan,Process Area, Hub Balochistan RO Plant,Cooling Tower & Boiler Plant .
|
Jul-07
|
Apr-11
|
M/s. Bosicor Oil Pakistan
|
|
20
|
JapanPower Generation Main Engine Hall, Workshop, Water Treatment Plant, Treated Water Tanks, Cooling Tower, Pump & Boiler Houses, Sludge Treatment Plant, HFO Tanks Warehouse, Admin Block & Grid Station at Raiwind, Lahore
|
Jun-96
|
Jan-98
|
M/s. Siemens Pakistan M/s. Akber & Associates M/s. Shakeel Haider
|
|
21
|
Indus Motor Press Shop Civil works for process Area
|
Jan-07
|
Apr-08
|
M/s. A.A. Associates
|
|
22
|
Novatex Main Plant-II Landhi
|
Aug-05
|
Jul-06
|
M/s. A.A. Associates
|
|
23
|
Master Motor Corporation Extension Works of Truck Assembly Plant, Karachi
|
Jul-04
|
Jan-05
|
M/s. Akbar & Associates
|
|
24
|
Walls Ice Cream Plant Civil, Plumbing, Elect., & HVAC Works for Unilever, Lahore.
|
Jun-94
|
Mar-95
|
M/s. Naveed Anwar & Associates
|
|
25
|
Karachi Grains (Pvt) Ltd. Processing Plant & Rice Mill, Bin Qasim
|
Oct-02
|
Oct-03
|
M/s. Akbar & Associates
|
|
26
|
Nippon Safety Glass Ltd. Civil, Plumbing & Electrical Works
|
Oct-97
|
Apr-98
|
M/s. Akbar & Associates
|
|
27
|
Procon Engg. (Pvt.) Ltd. Civil Works
|
Nov-98
|
Jul-99
|
M/s. Akbar & Associates
|
|
28
|
National Institute of Leather Tech. Civil, Plumbing Works
|
Sep-95
|
Dec-96
|
M/s.Associates Akbar
|
|
29
|
Shan Food Factory Korangi, Karachi
|
Nov-05
|
Feb-07
|
M/s. Gul & Thariani
|
|
30
|
Macpac Films Ltd.
|
Aug-03
|
Sep-04
|
M/s. A.A. Associates
|
|